The railways in Stockholm-Mälardalen are continuously being maintained and improved. This means that parts of the railway network periodically need to be completely, or partially shut down.
The information about planned track work is preliminary, exactly how the trains will run during this time is determined in more detail closer to that period.
Search your trip in the app Mälardalstrafik and on Mälardalstrafik.se to see the updated timetable.
Please note that travel time may be longer than usual when trains are replaced by buses.
2026
May
Gävle-Skutskär
Period: May 4-10
Affected lines:
- Uppsala-Gävle
Train services are replaced by buses between Gävle and Skutskär due to a planned switch replacement at Gävle Central Station.
Flen–Stockholm
Vagnhärad–Stockholm
Stockholm–Södertälje Syd
Period: May 13–17
Affected lines:
-
Hallsberg–Katrineholm–Stockholm
-
Norrköping–Nyköping–Stockholm
-
Örebro–Eskilstuna–Stockholm–Uppsala
Mälartåg’s three lines operating south of Stockholm will be affected by track work in Järna during the Ascension Day weekend. The work is related to the construction of the new Ostlänken railway. All train traffic will be replaced by buses on the routes Flen–Stockholm, Vagnhärad–Stockholm, and Stockholm–Södertälje from Wednesday, May 13 at 22:00 until Sunday, May 17 at 14:00. Replacement buses will only stop at Flemingsberg for the first and last departure of each day.
June
Västerås–Sala
Period: June 7–18
Affected line: Linköping–Eskilstuna–Västerås–Sala
Trains will be replaced by buses between Västerås and Sala from Sunday, June 7 to Thursday, June 18 due to track work involving the renewal of switches and rails.
Linköping–Norrköping
Period: June 8–14
Affected line: Linköping–Eskilstuna–Västerås–Sala
Trains will be replaced by buses between Linköping and Norrköping from Monday, June 8 to Sunday, June 14 due to track maintenance work.